  • iconThe proposals are worked out for a minimum of three months’ test duration. The price may be reduced if testing duration is increased.
  • iconThe loading, unloading and transport charges are in our scope. Please note that these prices are site location specific.
  • iconThe cost of any damage due to our personnel to the vehicle or load bank is in our scope. But if customer personnel are involved in any damage to the vehicle or load bank, the cost will be borne by the customer
  • iconThe cost of the cable which is to be used for connection of load bank with customer equipment is in our scope.
  • iconThe cost of connection accessories, if any, for connecting the load bank to the customer’s equipment is not in our scope. will be informed in advance.
  • iconThe cost of Maintenance/Troubleshooting of a load bank is in our scope. The Maintenance/Inspection/Troubleshooting will be carried out by our personnel before starting testing on a new site. This cost involves labor as well as material cost.
  • iconThe lodging/boarding of our personnel is in our scope.
  • iconA single PO with 3 months duration is mandatory for the customer.
  • iconThe Junction boxes required for connection of Aux Supply to all load banks is in our scope.
  • iconThe central Consoles required for networking of multiple load banks is in our scope.
  • iconThe MODBUS/ETHERNET Cables required for networking of load banks is in our scope.
  • iconThe expense of deputation of Technicians onsite during testing is in our scope.